Hexagon scheduled maintenance on November, 24th 9:00

We will have a planned hexagon maintenance on November, 24th and 25th.
The maintenance will start on 24th at 9:00 and we expect it will take
around 2 days.

The job submission system has reservation in place such as the jobs
which are not able to finish before the maintenance will not be started.

We are planning to do the following during the maintenance window:
* Update Cray Management Software to 7.2.UP02
* Update Cray Linux Environment to 5.2.UP02
* Update Lustre file system on /work and /work-common
* Apply different firmware updates and patches
* Install newer libraries, compilers and tools

IMPORTANT!: After the maintenance, the default MPT will be 7.x (MPICH
3.1). All software will have to be recompiled. We will come with the
details and options after the maintenance.