Fimm cluster will have down time 14th of May

Because of new equipment we need to expand the electric power in our machine room. We have therefore reserved the fimm cluster from 06:00, 14th of May. Long jobs not able to complete before the downtime will not be able to start.

The exact length of the downtime is currently unknown, but should not last more than half a day. We will provide more information as soon as we know more.

Update May 12th: We also discovered some issues with our file systems. We will therefore use this opportunity to perform complete file system checks. The down time will therefore be longer.

Update May 13th: The power shutdown will be at 10:00 tomorrow. We will make fimm unavailable from 09:00 because of needed upgrades.

Update May 14th 09:30: Todays power shutdown has been postponed until tomorrow at 07:00. We will still use the current down time to perform some maintenance.

Update May 14th 18:00: The file system checks are still not finished. We will monitor the progress through the evening. Fimm will be unavailable until after power shutdown tomorrow.

Update May 15th 08:55: Fimm is now available for usage again.