Downtime

There will be a scheduled downtime on fimm and its filesystems starting Monday January 21st at 0800. This is due to a replacement of the cooler in the machineroom.

We are very sorry for the inconvenience this very short notice may cause you.

The workmen responsible for the replacement have not given us an estimated time for when the cooling will be in place, but the work is expected to take about 2 days. More information will be posted here when we know it.

Update Monday, 1730: The coolers are in place and we are waiting for the plumbers to connect them to the cold-water system.

Update Tuesday, 1115: The plumbers have started the work connecting the coolers. Due to complications in this it is expected to be at least until Thursday afternoon before we can turn on the cooling again.

Update Friday, 1130: Fimm login node will be rebooted and upgraded shortly. This upgrade should take about 30 minuttes.
The plumbers are still working with the cooling, but we hope to be up and running later today.

Update Friday, 1140: Fimm login node has now been upgraded.

Update Friday, 1515: The cooling is now in place and fimm is again operational.

The old cooler (soon to be replaced) has failed.
Therefore the fimm cluster had to shut down to avoid overheating.

Update, 14:45: We now have the fimm frontend with filesystems operational for the moment. The queue will accept jobs, but they will not start since the nodes are not up. See note about scheduled downtime due to cooling system upgrade.

Update, Dec. 13th, 09:10: Due to limited cooling the frontend will be unavailable until the scheduled downtime has been completed.

Update, 19th 16:30: The cooling is now started again (see also updates on the schedule downtime note).

There will be a scheduled downtime on fimm and associated services starting on Thursday 13th Dec. The length of the downtime is uncertain at this time, but we expect to be up again on Tuesday 18th Dec.

The downtime is due to a major cooling system upgrade in the machineroom. We expect to need a second, smaller, downtime to finalize this upgrade in January.

Further information will be posted here when we know more.

Update, 12th 14:45: Because of the cooling failure (see other note above) the work on the cooling upgrade will start earlier.

Update, 13th 09:10: The frontend will now be unavailable until upgrade is completed.

Update, 17th 19:00: The expected startup of the cooling system on Tuesday has been delayed. We estimate the startup of the power and cooling systems around 12:00 Wednesday.

Update, 19th 12:00: The expected startup of the cooling system has been delayed for a couple of hours.

Update, 19th 16:30: Finally fimm is up and running again.

The login node on fimm will be rebooted today at 16:30.
This is related to the switch failure. A reboot is needed to get the system running correctly again. The machine should be up within minutes.

All jobs, except interactive, should be unaffected by the reboot.
Interactive jobs will be killed.

Update: 17:15: Fimm booted and running as normal.